Baku sleeper production plant
THOSTI personnel services:
- Planning of entire works.
 - Coordination of entire purchasing.
 - Technical supervision during entire construction phase.
 - Suitability testing of raw materials.
 - Sleeper and concrete design.
 - Approval tests.
 - Works commissioning.
 - Personnel training.
 
Data
| Project | Trans-Caucasian Rail Link Project | 
|---|---|
| Country | Azerbaijan | 
| Client | ADDY (Azerbaijan Railways Authority)  | 
                              
| Year of construction | 2002 | 
| Processing duration | 18 months | 
| Area | ~ 12.000 m² | 
| Product | Track sleepers typ B70, Russian track gauge | 
| Sleeper system | THOSTI-BBRV (B70) | 
| Capacity | 270.000 track sleepers/year | 
    Image gallery