Nuremberg asphalt mixing plant
THOSTI personnel services:
Planning of the entire works including site preparation (bomb disposal service, dewatering, green planting) and drawing up application documents.
Coordination of entire purchasing.
Technical supervision during entire construction phase.
Works commissioning.
Data
Project | Nuremberg asphalt mixing plant |
---|---|
Country | Germany |
Client | ROBA Baustoff GmbH |
Year of construction | 1997 |
Processing duration | 12 months |
Area | 10.000 m² |
Production | Asphalt |
Capacity | 250 t/h |