Trikala sleeper production plant
THOSTI personnel services:
- Planning of entire works.
- Coordination of entire purchasing.
- Technical supervision during entire construction phase.
- Suitability testing of raw materials.
- Sleeper and concrete design.
- Approval tests.
- Works commissioning.
- Personnel training.
Data
Project | Trikala sleeper production plant |
---|---|
Country | Greece |
Client | Strotires S.A. |
Year of construction | 1998 |
Processing duration | 12 months |
Area | ~ 10.000 m² |
Product | Track sleepers type B70 |
Schwellen System | THOSTI-BBRV |
Production capacity | 200.000 track sleepers/year |